Once a project actually starts, it is important to monitor the
progress to ensure that everything is going according to the plan. The key to
good project control is measuring actual progress and comparing it to planned
progress on a timely and regular basis and taking any needed corrective action
immediately.
Establish
project start and completion times
To establish a basis from which to calculate a schedule using
the estimated duration for the activities, it is necessary to select an
estimated start time for when the project is expected to begin and a required
completion time for when the project must be done. These two times (or dates)
define the overall window or envelope, of time in which the project must be
completed.
The sponsor or customer often states the project required
completion time in the project charter, request for proposal (RFP), or the
contract – for example, the project must be finished by June 30,
the feasibility study must be completed in time for the board meeting on
September 30, or the annual reports must be in the mail by January 15.
The contractor, however, may not want to commit to completing
the project by a specific date until the customer has approved the contract. In
such cases, the contract may state, “The project will be completed within 90
days after signing of the contract.” Here, the overall project time is stated
in terms of a cycle time (90 days) rather than in terms of specific calendar
dates.
Developing
Project Schedule
Once you have an estimated duration for each activity in the
network and have established an overall window of time in which the project
must be completed, you must determine (based on durations and sequence) whether
the project can be done by the required completion time. To determine this, you
can develop a project schedule that provides a timetable for each activity and shows:
1. The earliest
times (or dates) at which each activity can start and finish, based on the
project estimated start time (or date).
2. The latest
times (or dates) by which by which each activity must start and finish to
complete the project by its required completion time (or date).
Incorporating changes into the schedule
During the project changes may occur that have an impact on
the schedule. As was noted earlier, these changes might be initiated by the
customer or the project team, or they might be the result of an anticipated
occurrence. Here are some examples of changes initiated by the customer:
1. A home
buyer tells the builder that the family room should be larger and the bedroom
windows should be relocated.
2. A customer tells
the project team developing an information system that the system must have the
capability to produce a previously unmentioned set of reports and graphics,
which requires additional new elements in the database.
These types of changes represent revisions to the original
project scope and will have an impact on the schedule and budget.
No comments:
Post a Comment